Progress Energy Florida plans to build a new 69-kilovolt transmission line in western Orange County.
The project will begin at the existing Clarcona substation, at Apopka Vineland Road, run along McCormick Road, and end at the planned Crown Point substation, on West Road. The single, concrete poles will range from 65 to 100 feet tall.
Preliminary work, such as clearing trees and installing foundations, is scheduled to begin in July 2010. Construction is scheduled to begin in August 2010. The new line and substation are expected to be operational by early 2011. Schedules are subject to change.
As the area's population grows, the line will ensure the community continues to receive reliable electricity.
If you have questions about this project, please contact Project Manager Van Rushing at Van.Rushing@pgnmail.com or by calling 1-888-250-5196. Inquiries also may be mailed to Progress Energy, Attn: Van Rushing NP3D, 3300 Exchange Place, Lake Mary, FL 32746.
|